Esholt WWTW, Bradford | Yorkshire Water

 Culvert Cleaning & CCTV Survey 

2x Silos

Cleaned

 
 
 
 
 

4

Days completed in

 
 
 
 
 
 
 

£15,000

Contract Value

 
 
 
 
 
 
 
 

Project Overview

LOCATION

Esholt WWTW, Bradford

SCOPE

MRMS successfully excavated 130 m³ of cake from 2 blocked silos at Esholt WWTW within 4 days of emergency mobilisation – fully cleaning the silos, clearing the screw shafts, and enabling Yorkshire Water’s repair contractor to complete all works on programme.

PROGRAMME

4 days

CONTRACT VALUE

£15,000

Method of Works

Emergency Overnight Mobilisation

Lowloader with specialist grab and tractor trailers mobilised on Friday night for an early-start Saturday morning response.

Grab Cake Extraction

Specialist grab used to extract cake from within the tight HGV tipping access through to the top of the silo, loading directly into tractor trailers.

Cake Haulage to Conditioning Pad

Loaded trailers transported cake to the conditioning pad at the far end of the site for disposal and treatment.

Specialist Grab for Deep Clearance

Specialist grab attachment used to clear cake from between silo strengthening supports and within the bottom divided screw shaft chambers.

Recycler Jet Wash & Clean Down

Recycler unit deployed to jet and dilute remaining cake, washing down and around all screw shafts to prepare silos for repair works.

Site photography

Key Challenges & Highlights

Rapid Emergency Response

Works were instructed on a Friday and required overnight mobilisation of a full equipment train – specialist grab, tractor trailers and recycler – to be set up and operational by Saturday morning.

Extremely Confined Working Conditions

The tight HGV tipping access above the silo and the narrow internal chambers severely restricted plant manoeuvring. The specialist grab was essential to reach material within the strengthening supports and screw shaft divisions.

Confined Space Excavation

Working deep within the cake silos required the specialist grab to clear blocked material without damaging the silo structure or screw shaft mechanisms.

130 m³

Cake
Removed

 
 
 
 
 

2 Silos

Fully
Cleaned

 
 
 
 
 

4 days

Programme
Delivered

 
 
 
 
 
 
 
 
 
 

£15k

Contract
Value