Culvert Cleaning & CCTV Survey | Kier NR&N

 Culvert Cleaning & CCTV Survey 

50m

Culvert Length

 
 
 
 
 

8

Days completed in

 
 
 
 
 
 
 

£19,490

Contract Value

 
 
 
 
 
 
 
 

Project Overview

LOCATION

Whitchurch, SY13 1RS

SCOPE

Culvert cleaning and CCTV survey following a major breach on the Llangollen Canal, restoring drainage and assessing structural condition.

PROGRAMME

8 weeks

CONTRACT VALUE

£19,490

Method of Works

Culvert Clean & CCTV

~50m of 1200mm x 1200mm brick culvert cleaned and surveyed to full WRc standard

Downstream Twin Pipes

~33m of twin 225mm clay pipes cleaned and CCTV completed (Stage 2)

100% Silt Removal

All pipes 100% full of debris due to the breach – finished silt levels reduced to less than 10%

Portable Equipment Deployed

Material stockpiled at End B and loaded into 20-tonne haulage lorries for disposal.

Key Challenges & Highlights

Difficult Access

Inlet side became a sand pit from the canal breach. Outlet accessed via active plant track across wet farmland, requiring full portable setup.

Live Site Co-ordination

Works ran in tandem with ongoing major earthmoving operations, requiring continuous programme co-ordination to keep both scopes on track.

Technical Complexity

Culvert location and 100% silt blockage required multiple equipment configurations and expert planning to safely clean and survey.

Site photography

Project Summary

Delivered On Time. On Budget. To Specification

Culvert cleaned, CCTV completed, and drainage restored – allowing water to drain naturally off the field and the watercourse to function as intended.

50m

Culvert
Cleaned

 
 
 
 
 

33m

Twin Pipes Cleaned

 
 
 
 
 
 
 

8 days

Programme
Delivered

 
 
 
 
 
 
 
 
 
 

<10%

Final Silt
Level